April 2007:  Work continues

This picture (taken April 20, 2007) shows a group of volunteers working on the site in preparation for the soon to be opening of the new church.
As of April 2007,    Sheetrock finishing and painting are nearly complete. Basement and nave ceileinfgs are naerly done, Tile is being laid. Stairs finished. It will only be a few more weeks to completion.

The expected use is now June. These plans still include many deferred elements. Although these decisions will be made as the project progresses, some items currently planned for deferral are the onion domes, new commercial kitchen appliances, finishes for floors and trimwork, air conditioning, optional bathrooms, etc.  These and many other elements will be added over years as funding is available. Please consider helping with a donation of any size.  