August  18 2005:  The windows are now installed.

This picture (taken 08/18/05) shows the roofing and all windows are installed. Cedar siding was delayed and will be ordered this week. Installation will begin in September.
As of August 18, 2005,    Roofing is complete. Windows are installed. Slate installation on the porch floor has started. Electric and HVAC are expected to start soon.

Providing funds are available, the building may be ready for use in late 2005, although with many deferred elements. Although these decisions will be made as the project progresses, some items currently planned for deferral are the onion domes, new commercial kitchen appliances, finishes for floors and trimwork, air conditioning, optional bathrooms, etc.  These and many other elements will be added over years as funding is available. Please consider helping with a donation of any size.  
Latest Project Status
Read More About
Pictorial Chronology