April 20, 2006:  Spring returns

This picture (taken 04/16/06) shows that most of the cedar siding is installed. The lower level and a few boards on the north side remain. What isn't visible is that electric, heating and plumbing are nearly complete as well. The end is beginning to be seen.
As of April 2006,    Major mechanical and electrical work is complete. Most siding is done.

The expected use is now late summer 2006 or later depending on funding. These plans still include many deferred elements. Although these decisions will be made as the project progresses, some items currently planned for deferral are the onion domes, new commercial kitchen appliances, finishes for floors and trimwork, air conditioning, optional bathrooms, etc.  These and many other elements will be added over years as funding is available. Please consider helping with a donation of any size.  