August 2006: Exterior nearly complete
This picture (taken August 30, 2006) shows all of the cedar siding is installed. Site excavation has continued to complete the parking area. The well is installed and plans for finishing the site work installing the fuel and septic systems are complete. The exterior has received a second coat of stain and the traditional foundation skirt is complete.
As of August 2006, Most exterior work is done. Insulation is complete.
The expected use is nowspring 2007 or later depending on funding. These plans still include many deferred elements. Although these decisions will be made as the project progresses, some items currently planned for deferral are the onion domes, new commercial kitchen appliances, finishes for floors and trimwork, air conditioning, optional bathrooms, etc. These and many other elements will be added over years as funding is available. Please consider helping with a donation of any size.